What is a project time estimator?
A project time estimator replaces the single guessed number with three estimates per task — optimistic, most likely, pessimistic — combined by the PERT formula into an expected duration that respects how projects actually behave. Single-point estimates fail in a predictable direction: they describe the world where nothing goes wrong, quoted to a client who will hold you to them in the world where things do.
Break the project into tasks, estimate each three ways, and let the weighted maths — plus an explicit buffer — produce a number you can defend.
How this estimator works
Add a row per task, adjust the buffer for how uncertain the project feels, and set your real working day — the estimator returns per-task expected times, all three totals, and the buffered figure to quote from.
The maths, worked step by step
expected per task = (optimistic + 4 x most likely + pessimistic) ÷ 6
total with buffer = expected total x (1 + buffer %) • days = total ÷ hours per day
Worked example: Design — (10 + 64 + 28) ÷ 6 = 102 ÷ 6 = 17.0 hours. Build — (20 + 120 + 52) ÷ 6 = 192 ÷ 6 = 32.0 hours. Expected total: 49.0 hours. Buffer: 49.0 x 1.15 = 56.35 hours. Days: 56.35 ÷ 8 = 7.04. The 4x weight on "most likely" is the whole idea: the middle estimate carries the plan, while the extremes pull it honestly toward risk.
Why three estimates beat one
| Estimate | What it describes | What freelancers usually quote |
|---|---|---|
| Optimistic | Everything works first time; feedback is instant and kind | This one — renamed "the estimate" |
| Most likely | A normal run: some friction, some waiting, ordinary focus | Rarely asked for |
| Pessimistic | Tools break, feedback contradicts itself, life intervenes | Treated as negativity instead of information |
PERT comes from 1950s US Navy project management, built for programmes where a single optimistic number could sink a schedule. The formula's endurance is the point: it forces the estimator to name the bad case out loud, in hours, before the client hears a date.
The buffer is not padding — it is the plan for reality
Even a perfect PERT estimate covers only the tasks you listed. The buffer covers everything else: the day lost to a sick child, the client who replies on Thursday instead of Monday, the tool update that breaks your workflow. 10-15% suits familiar work for known clients; 20-25% is honest for new clients, new technology or fixed deadlines. Feed the buffered total into the Project Pricing Calculator as your hours figure and the quote inherits the same realism.
Break work down until estimates get boring
Three-point estimation only works on tasks small enough to picture. "Build the website — 40, 80, 200" is a guess wearing a formula. "Set up hosting and CMS — 1, 2, 4", "Product page template — 4, 7, 14" are estimates. A useful rule: if a task's pessimistic figure is more than four times its optimistic one, the task is actually several tasks, or an unknown that needs research before it can be estimated at all. Ten boring rows beat three dramatic ones.
What this estimator leaves out
- Dependencies. Tasks that must wait for other tasks (or for the client) stretch the calendar beyond the sum of hours — days here are working days of effort, not a delivery date.
- Your other clients. A 7-day estimate inside a week already sold to someone else is a scheduling problem, not an estimating one.
- Learning curves. First time with a tool or industry? The pessimistic column is where that honesty belongs.
- Scope growth. New tasks appearing mid-project need new rows and a new conversation — the estimator cannot absorb silent additions.
Sources & References
- Wikipedia — Program evaluation and review technique (PERT): origin and method
- Wikipedia — Three-point estimation: the (O + 4M + P) ÷ 6 weighted average
Every figure in this guide was calculated with this page's own formulas, so you can reproduce each one exactly by entering the same numbers above.