What is a labour cost calculator?

A labour cost calculator turns a crew and a schedule into the true cost of the labour on a job. The wage line is the easy part — workers times hours times rate — and it is also the part that loses contractors money, because wages are not what labour costs. On top of every wage sit the employer's payroll taxes, workers' compensation premiums, insurance and benefits: the burden. Underprice the burden and a won bid quietly becomes an unpaid one; the crew was never as cheap as the wage line made it look.

This page builds the labour figure the way a bid should: regular pay, overtime pay and per-diem as separate visible lines, burden applied to wages only and shown as its own amount, and the outputs a bid is actually assembled from — total labour cost, cost per worker, and total man-hours. It is a job-costing tool. It does not run payroll, compute anyone's income tax, or produce take-home pay; for personal pay figures the Salary Calculator is the right page, and payroll itself belongs in payroll software.

How this labour cost calculator works

Quick answer: Total labour cost = regular pay + overtime pay + per-diem + burden on wages. A crew of 4 at 8 hours a day for 5 days at $25 an hour earns $4,000 in wages over 160 man-hours; at a 20% burden the employer's true cost is $4,800.

The schedule comes first: workers, hours per day, days. Overtime is entered as extra hours per worker across the whole job, at a multiplier — the convention here is that overtime sits on top of the regular schedule, which matches how site hours actually accumulate. Per-diem is a flat daily allowance per worker. The burden percentage is then applied to the wage lines (regular plus overtime) and never to per-diem, because per-diem is an expense allowance, not wages — the breakdown shows the burden base so you can see exactly what was charged.

The maths, worked step by step

Four multiplications and an addition:

man-hours = workers x hours per day x days (plus workers x overtime hours).
regular pay = man-hours (regular) x rate.
overtime pay = workers x overtime hours x rate x multiplier.
total = regular + overtime + per-diem + burden% x (regular + overtime).

For the example crew: 4 x 8 x 5 = 160 man-hours; 160 x $25 = $4,000; no overtime, no per-diem; burden 20% x $4,000 = $800; total $4,800, which is $1,200 per worker. In Excel, with workers in B2, hours in B3, days in B4 and rate in B5, wages are =B2*B3*B4*B5 and the loaded total at a burden in B6 is =B2*B3*B4*B5*(1+B6). Test any sheet against the known case first: 4, 8, 5, $25 and 20% must return $4,000 of wages and a $4,800 total.

The employer burden, broken down

Burden is not one tax; it is a stack of smaller ones, and its size is mostly set by two things — where you are, and how dangerous the work is rated. The components below are typical ranges for construction in North America and similar systems; they are labelled as ranges because every jurisdiction and insurer sets its own numbers.

Burden componentTypical range (% of wages)What drives it
Payroll taxes & social contributions7-12%Statutory — social security, unemployment insurance, pension contributions
Workers' compensation insurance3-15%+Trade risk class — roofing and steel erection at the top, finishing trades lower
Liability & other insurance1-4%Policy limits and claims history
Benefits (health, pension, holiday)0-10%What the employer offers; union agreements set many of these
Total working range10-30%Most construction crews land between a fifth and a quarter

Official statistics tell the same story at economy scale: the US Bureau of Labor Statistics' Employer Costs for Employee Compensation release puts benefits alone at roughly a third of total compensation across private industry. Two practical rules follow. First, never bid from the wage line — bid from the loaded line. Second, get your own burden rate from your payroll: one division (last quarter's employer costs over last quarter's wages) replaces every estimate in this table, and it is the single most valuable number in a contractor's pricing.

Overtime and per-diem

Overtime is where job costs leak, because it is bought at the multiplier and usually spent at the end of the job, against a deadline, when nobody is counting. Cost it deliberately: the hours are entered per worker for the whole job, the default multiplier is 1.5x, and burden applies to overtime wages exactly as to regular wages — payroll taxes and compensation premiums do not stop at 40 hours. What counts as overtime legally, and whether it is 1.5x, 2x, or governed by a union agreement, varies; the calculator applies the rule you set.

Per-diem is the opposite kind of line: flat, predictable, and burden-free. It buys the crew's meals, lodging or travel on away work as a daily allowance instead of a shoebox of receipts. Enter it per worker per scheduled day. If a job runs long, per-diem runs with it — one more reason the days figure deserves the same honesty as the hours.

Blended rates for mixed crews

Real crews are not one rate: a lead hand, two tradespeople and a labourer might stand at $38, $30, $30 and $19. The calculator takes one rate, so use the blend — total hourly cost divided by heads: (38 + 30 + 30 + 19) / 4 = $29.25. The total is identical to costing each person separately whenever the whole crew works the same schedule, which on most jobs they do. Where schedules genuinely differ — the supervisor attends two days, not five — cost that person in a second run and add the totals; the breakdown keeps each run auditable.

Worked examples

All three rows use this page's own method — burden on wages only — so each can be reproduced above in seconds.

JobCrew & termsWagesBurdenTotalMan-hours
One-week fit-out4 workers, 8 h x 5 days, $25/h, burden 20%$4,000$800$4,800160
Weekend push6 workers, 8 h x 3 days, $30/h, 2 OT hours each at 1.5x, burden 15%$4,860$729$5,589156
Away job, two weeks3 workers, 8 h x 10 days, $22/h, $40/day per-diem, burden 25%$5,280$1,320$7,800240

Check the middle row by hand: regular pay is 6 x 8 x 3 x $30 = $4,320; overtime is 6 workers x 2 hours x $30 x 1.5 = $540; wages total $4,860, and 15% of that is $729, giving $5,589. The third row shows the burden rule in action: the $1,200 of per-diem (3 x 10 x $40) joins the total after burden — 25% falls on the $5,280 of wages alone ($1,320), and $5,280 + $1,200 + $1,320 = $7,800. Pair either row with the Construction Material Estimator and you have both halves of a small bid.

What this calculator leaves out

  • Payroll itself. No individual taxes, deductions, net pay, payslips or filings. This is costing, not payroll — see the note in the form and use payroll software or an accountant for the real thing.
  • Materials, plant and equipment. Labour only. Cost materials with the category's other tools and add the lines.
  • Overhead and profit. Rent, vehicles, office, estimating time — and your margin — belong on top of the total, in your bid build-up, not hidden inside a labour rate.
  • Non-productive time. Weather days, waiting on other trades, inductions and travel between sites consume paid hours the schedule above does not model. Experienced estimators pad the days or the man-hours for it; the calculator takes the schedule you give it.
  • Legal overtime rules. Thresholds and multipliers are your inputs. What the law or a union agreement requires in your place governs the real job.

None of this makes the figure useless — it makes it a costing figure. Feed it your real burden rate and a honest schedule, and it will tell you what the crew costs before the job teaches you the expensive way.

Sources & References

Every figure in this guide was calculated with this page's own method and rounding, so you can reproduce each one exactly by entering the same numbers above.